ISQI CTFL_Syll_4.0 Exam Overview:
| Certification Vendor: | ISTQB (International Software Testing Qualifications Board) |
|---|---|
| Exam Name: | ISTQB Certified Tester Foundation Level (CTFL) v4.0 |
| Exam Number: | CTFL_Syll_4.0 |
| Real Exam Qty: | 40 |
| Exam Price: | 250 USD |
| Related Certifications: | CTAL-TTA (Test Analyst) CTAL-TM (Test Manager) CTAL-TA (Technical Test Analyst) |
| Available Languages: | Chinese, French, Polish, Dutch, Spanish, German, Czech, English, Portuguese (Brazilian), Japanese |
| Exam Duration: | 60 minutes |
| Exam Format: | Multiple choice (single and multiple correct answers) |
| Passing Score: | 65% |
| Certificate Validity Period: | Lifetime (no expiration, subject to ISTQB exam version policy) |
| Sample Questions: | ISQI CTFL_Syll_4.0 Sample Questions |
| Exam Way: | Online proctored (remote) and in-person at accredited exam centers worldwide |
| Pre Condition: | No formal prerequisites required. Foundation level is the entry-level certification for anyone involved in software testing. Prior experience in software development or testing is recommended but not mandatory. |
| Official Syllabus URL: | https://www.istqb.org/ |
ISQI CTFL_Syll_4.0 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Tool Support for Testing | 0% | - Tools Support
|
| Managing the Test Activities | 25% | - Test Planning
|
| Fundamentals of Testing | 20% | - The Psychology of Testing
|
| Test Analysis and Design | 20% | - Characteristics of Good Tests
|
| Static Testing | 15% | - Static Testing Basics
|
| Testing Throughout the Software Development Lifecycle | 20% | - Software Development Lifecycle Models
|
ISQI ISTQB Certified Tester Foundation Level (CTFL) v4.0 Sample Questions:
Which one of the following statements correctly describes the term 'debugging'?
- A. Debugging is the development activity that finds, analyses and fixes defects.
- B. There is no difference between debugging and testing.
- C. Debugging is a confirmation activity that checks whether fixes resolved defects.
- D. Debugging is of no relevance in Agile development.
Correct Answer: A 🗳️
Explanation: Only visible for TopExamCollection members. You can sign-up / login (it's free).
Your team is developing a new functionality for an employee management system, a Simple Reporting feature. The team is tasked with estimating the test effort required to test this feature.
The team used the standard three-point estimation method to provide the predicted effort.
The team came up with the following estimates:
- in the optimistic scenario, the testing can be done in 1 hour
- in the most likely scenario, the testing can be done in 2 hours
- in the worst-case scenario, the testing can be done in 9 hours
What is the team's final estimation of the test effort?
- A. 4 hours
- B. 3 hours
- C. 2 hours
- D. 6 hours
Correct Answer: B 🗳️
Explanation: Only visible for TopExamCollection members. You can sign-up / login (it's free).
Which ONE of the following statements about the objectives of confirmation and regression testing is the BEST?
- A. The purpose of regression testing is to confirm that the defect giving rise to a failure has been satisfactorily resolved. The purpose of the confirmation testing is to ensure that no defects have been introduced or discovered in unmodified areas of the software as a result of the changes made.
- B. The purpose of confirmation testing is to confirm that the defect giving rise to a failure has been satisfactorily fixed. The regression test aims to ensure that no defects have been introduced or discovered in modified areas of the software as a result of the changes made.
- C. Confirmation testing aims to confirm that the observed failure is not a false positive. The regression test aims to ensure that no defects have been introduced or discovered in unmodified areas of the software as a result of the changes made.
- D. The purpose of confirmation testing is to confirm that the defect giving rise to a failure has been successfully fixed. The regression test aims to ensure that no defects have been introduced or discovered in unmodified areas of the software as a result of the changes made.
Correct Answer: D 🗳️
Explanation: Only visible for TopExamCollection members. You can sign-up / login (it's free).
As a result of the joint evaluation of a product version with the customer, it has been concluded that it would be appropriate to retrieve an earlier version of the product and carry out a benchmark. Depending on the result, further development will be carried out based on the current version or the retrieved version.
Which mechanism, process, and/or technique will allow the specific version (including the testing work products) of a given software product to be restored?
- A. Defect management
- B. Risk management
- C. Change management
- D. Configuration management
Correct Answer: D 🗳️
Explanation: Only visible for TopExamCollection members. You can sign-up / login (it's free).
When is the detailed risk analysis for a story first conducted?
- A. Epic planning
- B. Release planning
- C. Iteration planning
- D. Project planning
Correct Answer: C 🗳️