PRINCE2 P3O Foundation Project Office2013 Sample Questions:
1. Which is a purpose of measuring Key Performance Indicators for a P3O?
A) Demonstrate a P3O's successes to the organization
B) Determine project progress against its plan
C) Identify areas of personal improvement for Project Managers
D) Identify the resources required within a P3O
2. What technique enables people to share experiences by connecting people to information or to other people?
A) Skills development and maintenance
B) Knowledge management
C) Complexity modelling
D) Management dashboards
3. What technique provides the benefit of checking the quality of the decision-support information being provided to the P3O?
A) Gated reviews
B) Business process swimlanes
C) Management dashboards
D) Capacity planning for resource management
4. What technique provides the benefit of checking the quality of the decision-support information being provided to the P3O?
A) Gated reviews
B) Business process swimlanes
C) Management dashboards
D) Capacity planning for resource management
5. Which of the following are recommended for the implementation of a P3O model?
1. Follow a recognized programme or project methodology
2. Define a budget and associated timescales to deliver
3. Appoint a P3O Sponsor
4. Use a programme approach to implement a single office P3O staffed by one individual
A) 2,3,4
B) 1,3,4
C) 1,2,3
D) 1,2,4
Solutions:
| Question # 1 Answer: A | Question # 2 Answer: B | Question # 3 Answer: A | Question # 4 Answer: A | Question # 5 Answer: C |