PMI Project Management Professional V5 Sample Questions:
1. 
Which of the following is the correct network diagram for the table?
A) Begin-A-B-C-D-E-End
B) Begin-A-C-D-E-End-B-D
C) Begin-A-C-D-E-End-B-C
D) Begin-A-B-D-E-End A-C-D
2. On what is project baseline development established?
A) Actual project cost and schedule
B) Approved product requirements
C) Revised project cost and schedule
D) Estimated project cost and schedule
3. An example of a group decision-making technique is:
A) multi-criteria decision analysis
B) majority
C) nominal group technique
D) affinity diagram
4. Inputs to the Define Activities process include:
A) Scope baseline, enterprise environmental factors, and activity duration estimates.
B) Scope baseline, enterprise environmental factors, and organizational process assets.
C) Project scope statement, resource calendars, and work performance information.
D) Project scope statement, approved change requests, and WBS dictionary.
5. A project management office manages a number of aspects including the:
A) Assignment of project resources to best meet project objectives.
B) Central coordination of communication management across projects.
C) Project scope, schedule, cost, and quality of the products of the work packages.
D) Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: D | Question # 3 Answer: B | Question # 4 Answer: B | Question # 5 Answer: D |