PRINCE2 Practitioner is an internationally recognized project management methodology that provides a structured approach for managing projects. It is a popular framework used by organizations worldwide to deliver projects effectively and efficiently. The PRINCE2-Practitioner Exam is designed to test the knowledge and skills of project managers who want to become certified in the PRINCE2 Practitioner methodology. Passing PRINCE2-Practitioner exam demonstrates that the candidate has a strong understanding of the PRINCE2 methodology and can apply it to real-world projects.


PRINCE2 Practitioner exam is designed for professionals who already possess a basic understanding of the PRINCE2 methodology and have completed the PRINCE2 Foundation certification. PRINCE2-Practitioner exam focuses on testing the application of the methodology in real-world scenarios and evaluating the candidate's ability to tailor the methodology to different project environments. PRINCE2 Practitioner Exam certification provides assurance to organizations that the certified professional has the necessary knowledge and skills to effectively lead and manage projects using the PRINCE2 methodology.

 

NEW QUESTION # 47
At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?

  • A. Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances.
  • B. There can be no time tolerances for any of the stages.
  • C. The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans.
  • D. All of the project level time tolerance can be allocated to stage 2.

Answer: D


NEW QUESTION # 48
A construction company that is one of ABC Company's key clients has agreed to provide a member of the staff
to review and comment on the 'e-learning course'.
Which stakeholder interest should the member of staff represent, and why?

  • A. Supplier, because this stakeholder provides the expertise required by the project.
  • B. Supplier, because this stakeholder is an external supplier.
  • C. User, because this stakeholder ensures that the project provides value for money.
  • D. User, because this stakeholder may train its staff using the 'e-learning course'.

Answer: C


NEW QUESTION # 49
The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.
Is this appropriate, and why?

  • A. Yes, because the change control approach should specify how the configuration item records are approved.
  • B. Yes, because the project should verify that the recorded status reflects the actual status of the products.
  • C. No, because the project manager should ensure that the change control approach is tailored to the project.
  • D. No, because the issue management and change control procedures can be treated as separate, but related, procedures.

Answer: A

Explanation:
Explanation/Reference:
Change Theme
Testlet 1
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.


NEW QUESTION # 50
The executive identified that there would be a benefit to the construction companies as their working time lost due to accidents would be reduced. This was included as a benefit to ABC Company in the business case for the Health and Safety Training Project.
Is this appropriate, and why?

  • A. Yes, because both tangible and intangible benefits should be included in the business case.
  • B. Yes, because the benefits to the customer are an essential part of business justification for a project.
  • C. No, because it is the customer's benefits that should be used to justify the project business case.
  • D. No, because ABC Company will not achieve their benefits if construction companies do not book the courses.

Answer: B


NEW QUESTION # 51
HOTSPOT
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.
Using the additional Information provided for this question In the Scenario Booklet, answer the following question.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Answer:

Explanation:


NEW QUESTION # 52
HOTSPOT
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff.
This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can be used once, more than once or not at all.
Column 1 contains a number of possible risk responses to the above risk. For each risk response, select from Column 2 the appropriate risk threat response type that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Hot Area:

Answer:

Explanation:


NEW QUESTION # 53
During the initiation stage, the project manager aligns the project's risk management approach to ABC Company's risk management policy. As a result, the project will use two risk registers, one for ABC Company's risks and one for external supplier risks.
Is this an appropriate application of the 'tailor to suit the project' principle, and why?

  • A. No, because a single risk register should be used to record risks to the project.
  • B. Yes, because the risk management approach should comply with the supplier's needs.
  • C. Yes, because project controls should take the project's environment into account.
  • D. No, because all three stakeholder interests need to be represented effectively on the project.

Answer: B

Explanation:
Explanation/Reference:
Business Case Theme
Testlet 1
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of E2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
* 20% discount for all repeat customers - not cost-effective and very short term
* A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year
* A series of television and press advertisements was too expensive
* A direct mail shot to all customers - benefit would be short term
* Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.


NEW QUESTION # 54
According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing
project is correct?

  • A. A Configuration Management Strategy is unnecessary for this project because the MFH document control
    process is documented. It is acceptable simply to reference this in the Quality Management Strategy.
  • B. A separate Configuration Management Strategy will be required for each of the suppliers within this project
    because each will have a different way of managing and storing products.
  • C. Every project needs a Configuration Management Strategy, even if the organization has existing
    configuration management standards, because every project has different circumstances.

Answer: C


NEW QUESTION # 55
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him.
They promote existing training courses to other training companies and existing customers.
End of the additional information.
The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?

  • A. Yes, because the project manager needs to receive confirmation that work has been completed and approved.
  • B. No, because the work package should be checked to confirm the reporting arrangements of the 'e- learning course'.
  • C. Yes, because a team plan to gain accreditation of the 'e-learning course' is required to be part of the work package.
  • D. No, because it is the configuration item record of the relevant product description that is updated, not the work package.

Answer: A


NEW QUESTION # 56
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
What statement applies to the Records section?

  • A. Move entry 6 to the Configuration Management Strategy because it defines the identification scheme for the project's products.
  • B. Move entry 8 to Tools and techniques because it refers to a filing technique.
  • C. Move entry 7 to Communication procedure because it refers to the method to be used for communication to external parties.

Answer: A


NEW QUESTION # 57
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Budgets section?

  • A. Delete entry 17 because the risk budget should be shown in the Risk Management Strategy.
  • B. Amend entry 15 because it should also include the cost of management activities.
  • C. Delete entry 16 because timescales should NOT be shown under the heading of budgets.
  • D. Add 'Cost tolerance - +£6k 1-£6k
  • E. Add 'Change budget - £500'.

Answer: B,E


NEW QUESTION # 58
The executive has set the following tolerances for stage 2:
Time (+/- 1 week)
Cost (+/- E20,000)
Scope (using MoSCoW prioritization technique)
Risk (based on the risk appetite defined in the risk management approach) These tolerances have been recorded in the stage plan. The project manager will report progress regularly via highlight reports to the project board and use exception reports to raise exceptions. In addition, the project assurance role will monitor the stage to provide confidence to the project board that exceptions are being reported.
How well does this apply the 'manage by exception' principle, and why?

  • A. It applies the principle poorly, because tolerances should be set for each stage against each of the six aspects of project performance.
  • B. It applies the principle well, because tolerances should be set for the related aspects of project performance for each stage.
  • C. It applies the principle well, because the project manager needs to control the project using discrete management stages.
  • D. It applies the principle poorly, because it is the regular reporting of progress that should give the project board the required confidence.

Answer: A


NEW QUESTION # 59
Scenario
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed user assurance for this project?

  • A. Remove because neither of these individuals are from the business functions to be outsourced.
  • B. Retain because selecting only one of them may cause unnecessary conflict.
  • C. Retain because they are able to help identify stakeholders and their communication requirements.
  • D. Retain because they are both very positive about outsourcing the selected business functions.
  • E. Retain because their divisions will be the major users of the outsourced services and they can provide the user perspective on the impact of any proposed changes.

Answer: C,E


NEW QUESTION # 60
None of the reviewers have proof-reading skills.

  • A. No action required.
  • B. Contact Project Assurance to find appropriate resources to come into the review.
  • C. Ask the reviewers present at the meeting to conduct a proof-reading exercise and pass any comments to the author within 2 days.
  • D. Record an action to request that Project Assurance identify a proof-reader who can, within the next 2 days, complete the check for typographical errors.

Answer: D


NEW QUESTION # 61
Which 2 statements explain why the CEO should be appointed as the Executive for this project?

  • A. He knows his job very well.
  • B. He has the authority to commit resources as required.
  • C. He restricts his visits to the engineering area.
  • D. He started the company 25 years ago.
  • E. He has an overall perspective of the business's strategic requirements.

Answer: B,E

Explanation:
Explanation


NEW QUESTION # 62
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him.
They promote existing training courses to other training companies and existing customers.
End of the additional information.
ABC Company uses a standard development model to develop courses and uses PRINCE2 to manage these projects. The objectives from the Health and Safety Training Project have been documented in the business plan of ABC Company. This business plan has triggered this project. As a result, to save time, the executive has decided to simplify the 'starting up a project' process. The project mandate will be adapted and becomes the project brief.
Is this appropriate, and why?

  • A. Yes, because the executive can initiate the project based on the project mandate by passing the
    'starting up a project' process.
  • B. No, because capturing lessons from previous projects identify lessons to be applied to this project.
  • C. No, because the project brief should be a statement which includes a fuller description of the project.
  • D. Yes, because the business outcomes are clear, the project brief can be a sample statement elaborating the mandate.

Answer: C


NEW QUESTION # 63
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
* Design for each month - correctly showing at public holidays and new company logo
* Selected photographs- 12 professionally-produced photographs, showing different members of staff
* Selected paper and selected envelope - for printing and mailing the calendar
* Chosen label design - a competition to design a label will be held as part of this project
* List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
* Create the customer fast using information from the Accounts and Marketing departments
* Confirm compliance with the Data Protection Legislation
* Create a design for each month - this will be done by the internal creative team
* Select and appoint a professional photographer
* Gather photograph design ideas from previous project and agree photographic session schedule
* Prepare a production cost forecast
* Select paper and envelope.
Stage 3 will include the activities to:
* Produce and select tie professionally-taken photographs
* Hold the label design competition and choose the label design
* Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the costs could vary considerably depending on the size of the package and the delivery service used. For the purpose of this project, the Project Manager has selected an appropriate service but feels that a corporate standard for postage would have reduced the time and effort invested. It could reduce the company's overheads by up to £20k per year. How should the Project Manager record this observation within the project?

  • A. Make an entry in the Lessons Log for future consideration by corporate management.
  • B. Make a note of the observation in the Daily Log to be transferred to a Benefits Review Plan at the end of the project.
  • C. Record the observation in an Exception Report to the Project Board.
  • D. Produce a project mandate, outlining the potential savings to be achieved by the introduction of a corporate standard.

Answer: A


NEW QUESTION # 64
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
CLOSING A PROJECT
Benefits relating to income and business reputation after the project has closed cannot be shown at project closure.
Which statement describes how the 'closing a project' process makes provision for this?

  • A. As part of the 'prepare planned closure' activity. It will be confirmed that the acceptance criteria defined in the project product description have been met.
  • B. As part of the 'prepare planned closure' activity. It will be confirmed that the project has delivered what was defined in the project product description.
  • C. As part of the 'hand over products' activity, the 'finalized materials' will be passed to the operational business environments.
  • D. As part of the 'hand over products' activity, the benefits management approach will be updated to include future activities for benefit measurement.

Answer: C


NEW QUESTION # 65
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Stakeholder analysis: Interested parties section?

  • A. Delete entry 12 because the printing of the calendars is outside of the scope
  • B. Delete entry 11 because the photographer is internal to the project management team.
  • C. Add 'Internal Creative Team'.

Answer: C


NEW QUESTION # 66
......


PRINCE2 Practitioner exam is a certification exam that validates the knowledge and skills of professionals in project management using the PRINCE2 methodology. PRINCE2 (PRojects IN Controlled Environments) is a globally recognized project management methodology that provides best practices and guidelines for managing projects. It is widely adopted across multiple industries and is considered the de-facto standard for project management excellence.

 